BUS 519 Assignment 4 Project Progress ( EQI in SIWA )
BUS 519 Assignment 4 Project
Progress ( EQI in SIWA )
Due Week 9 and worth
200 points
Note: The assignments are a series of papers
that are based on the same case, which is located in the Student Center of the
course shell. The assignments are dependent upon one another.
During the project
life cycle, project risk reviews and reports are required as previously
identified in the risk management plan. Two months after the project started,
the following events have taken place.
1.
The top-two (2)
threats have occurred.
2.
The top opportunity
has been realized.
3.
The project̢۪s risk
budget is already exhausted.
4.
The risk management
schedule has been shortened by two (2) months.
Write a five to seven
(5-7) page paper in which you:
1.
Analyze the impact of
those events on the project.
2.
Determine if any
mitigation activities are required and explain why.
3.
Determine if budget /
schedule changes are necessary and explain why.
4.
Update the risk
register and highlight the changes made. Provide the justification for the
changes.
5.
Use at least four (4)
quality resources in this assignment. Note: Wikipedia
and similar Websites do not qualify as quality resources.
Your assignment must
follow these formatting requirements:
·
Be typed, double
spaced, using Times New Roman font (size 12), with one-inch margins on all
sides.
·
Include a cover page
containing the title of the assignment, the student̢۪s name, the professor̢۪s
name, the course title, and the date. The cover page and the reference page are
not included in the required assignment page length.
The specific course
learning outcomes associated with this assignment are:
·
Given an information
requirement related to project risk management, determine the nature and extent
of information needed to effectively address the topic; efficiently locate,
determine the validity, and critically evaluate the resources; and apply the
information to accomplish the specific purpose (report, case analysis, factual
requirement, problem solving, and planning).
·
Use technology and
information resources to research issues in project risk management.
·
Write clearly and
concisely about project risk management using proper writing mechanics.